Since May is practically gone and this site was still a parking lot today when I drove by, I'm guessing they're waiting til the streetcar construction in that direct vicinity is complete before moving forward?
Whats going on with this project? I pretty much forgot about it.
Waiting for the flagpole to move maybe
The flagpole isn't impacting the start; and in fact it's essentially been decided to let it go at this point. For some time, the start of construction has been projected to be this month. Even if it doesn't happen this month all systems are still go presently.
Building permits have not been issued as of yet.
Yeah, Richard McKown talked about the results of the design meeting (regarding the flag) at the last BID board meeting (incidentally I made a suggestion he seemed to like [which is not to say it's feasible] that I should PM you about), so I knew what was up with that, I just didn't know if they were waiting to proceed until that meeting happened, which if so may have pushed start times back I was thinking.
The hotel developer is in no way waiting for resolution on the flagpole issue and is free to proceed at any time.
Whats happening here?
Is the city's request for more info publicly available somewhere?
On the city's permit system.
The process is:
1. Applicant submits form and info in aid of a building permit
2. City staff reviews and come back with request for more details and clarifications
3. Applicant answers
4. City staff again reviews
5. Repeat 3 & 4 until building permit is issued.
This project has been stuck on #2 for months. That is usually a sign the developer is not in any hurry for various reasons, the most common being that the submission of a building permit application (step #1) almost always coincides with seeking construction bids and financing. When those things aren't going well (need to rebid project, revise plans to reduce costs, can't get financing) the developer is in no rush to move past step #2 until those issues are resolved on their end.
I had a chance meeting with the general contactor a couple of weeks ago. He was on site - visiting from Fayetteville - and was here photographing the site and making plans for things like crane location and construction barricades. He expects construction to proceed relatively soon, but just as we were discussing schedule I was pulled away by a phone call.
Has this project died? What’s the hold up?
Was just told today they are moving forward.
However, they still have not responded to the City's request for items needed for their building permit application that came in June of last year.
There is some movement in the Bricktown Urban Design Committee regarding this project. It looks as though the owner has submitted revisions and received design approval.
https://www.okc.gov/departments/plan...vents-calendar
Click on the meeting you want to view, and if the agenda is available you can access it from there.
I have that link as one of my home pages, and check it when I get to the office. It really helps me keep track of everything that is moving around town.
I was able to find the agenda for the March meeting linked at https://agenda.okc.gov/sirepub/mtgvi...doctype=AGENDA, and that has the revisions PDF linked for download if you scroll down to 8.A.1 and click for the supporting matrials (the PDF download is at the bottom of the box over to the right).
The PDF link directly, though i understand that document links off the city website have a habit of not persistantly working and as such it may not work for anyone else.
Any updates?
https://newsok.com/article/5606174/q...building-spree
latest report is work won't start for another few months